Bardsley has a wealth of experience within the education sector, successfully delivering a wide range of facilities from small refurbishment to major new buildings for a variety of clients; nurseries, primary and secondary schools to higher and further education faculties. The projects have been provided via Partnering, Traditional and Design & Build procurement routes, all of which have provided excellent results. By recognising and understanding the objectives of the end users, be they; councils, universities, colleges, head teachers, staff and most importantly, the students, we have been able to deliver high quality facilities, when they are; on many occasions in live, occupied premises, while satisfying ever increasing design standards, legislation, sustainability and long term maintenance criterion.
| University of Liverpool Bio Science |
Click for more images |
Extension to the district heating mains to include trenching, civil works, fabrication of pipework and installation of all associated pumps, valves etc. |
Client: Uni of Liverpool Energy Co Ltd
Architect: Davis Langdon LLP
QS: Liverpool University FM depot
Start on Site: June 2011
Completion Date: September 2011 |
| Alder Grange Community Technology College |

Click for more images |
The design and build of a new 300 place, post 16 college to incorporate the following; science /creative expressive arts block, refurbishment of old science/arts areas for IT business administration, new corridor to humanities block to increase sizes of teaching spaces, floodlighting to the all-weather multi-use area and additional car parking and external works.
|
Client: Alder Grange Community Technology College
Architect: Hartington Flemming Worsley
QS: Glovers Project Services
Start on Site: December 2009
Completion Date: December 2010
|
| Liverpool Hope University |
Click for more images |
Construction of a new three storey steel frame teaching facility constructed to achieve ‘Very Good’ BREEAM rating. Selective demolitions, part re-roofing and general refurbishment works to the existing Warrington and Students Union buildings. All works carried out within the University’s live Hope Park Campus.
|
Client: Liverpool Hope University
Architect: Halsall Lloyd Partnership
QS: Tweeds
Start on Site: August 2009
Completion Date: September 2010
|
| Edge Hill University, Ormskirk |
Click for more images |
Construction of 2 storey steel framed building to form new facilities management central area.
|
Client: Edge Hill University
Architect: NJSR Chartered Architects
QS: MDP Project Services
Start on Site: December 2009
Completion Date: July 2010
|
| Rochdale 6th Form College |
 Click for more images |
Design and construction of a new six storey steel frame college facility including, a theatre with retractable seating, a refectory on the lower floor and café on the top floor, a drama suit with specialist dance flooring, this building is to be part clad in zinc and terracotta and part glazed and the roof top it to be a landscaped green roof.
|
Client: Rochdale 6th Form College
Architect: Seven Architects
QS: Davis Langdon
Start on Site: March 2009
Completion Date: August 2010
|
| Loreto 6th Form College, Manchester |
Click for more images |
The design and construction of a new five storey multifunctional building totalling approximately 6,794m², together with the refurbishment of the existing Ball Building and external works to be built to an Excellent BREEAM Rating.
|
Client: Loreto 6th Form College
Architect: Taylor Young Architects
QS: AA Projects
Start on Site: November 2008
Completion Date: August 2010
|
Click for more images |
Complete refurbishment and partial demolition works to existing site to create computer suite, offices and recreational areas, all within live campus.
|
Client: University of Bradford
Architect: Bowmanriley Architects
QS: Faithful and Gould
Start on Site: November 2009
Completion Date: February 2010
|
| Blackpool 6th Form College |
 Click for more images |
Design & Build of a three storey 6,000sqm steel framed teaching facility comprising of ICT suites, classrooms, library and staff rooms. Constructed using innovative design and brise solaire aero foil shading. Constructed to achieve a 'Very Good' BREEAM rating.
|
Client: Blackpool 6th Form College
Architect: DLA Architecture
Employers Agent: AA Projects
Contract Type: JCT 98 Standard
Start on Site: July 2007
Completion Date: August 2009
|
| Blackburn HE Facility College |
 Click for more images |
Design & Build of a five storey steel framed higher education centre to 7,343sqm of specialist teaching space incorporating; learning resource centre, refectory & servery, lecture theatre, administration, IT and general teaching classrooms.
|
Client: Blackburn College
Architect: Buttress Fuller Alsop Williams
Quantity Surveyors: Pearson Fraser
Start on Site: May 2008
Completion Date: August 2009
|
 Click for more images |
Estates rationalisation programme to provide 3,500sqm ofadditional teaching space, drama facilities and specialised performance rooms. Phase 1: Design & Build of a new two storey extension to the St Mary’s Building. Phase 2: Design & Build of the new five storey Lakeside Teaching Building.
|
Client: Cardinal Newman College
Architect: Ellis Williams Architects
Quantity Surveyors: AA Projects
Start on Site: November 2007
Completion Date: February 2009
|
 Click for more images |
Construction of a new 6th form College Campus, including teaching facilities, laboratories, lecture theatres and refectory.
|
Client: Bolton 6th Form College
Architect: Taylor Young
Structural Engineer: AJP
Start on Site: June 2007
Completion Date: July 2008
|
 Click for more images |
Design & Build of a four storey steel frame college building comprising of a performing arts theatre including; retractable seating, media and IT centre with interactive white boards and overhead projectors, learning resource, teaching accommodation, recording studios and refectory facilities.
|
Client: The Governor's of
Pendleton College
Architect: DLA Architecture
Employers Agent: AA Projects
QS: Turner and Townsend
Contract Type: JCT Standard
Start on Site: January 2006
Completion Date: September 2007
|
| University of Salford Law Building |
 Click for more images |
Design and construction of a new prestigious law school with teaching space, lecture theatre and library with associated external works. The three storey steel framed building is clad externally in curtain walling, Trespa Boarding, render and ETFE cushion cladding to the lecture theatre. The building utilises a semi passive ventilation system.
|
Client: The University of Salford
Architect: Broadway Malyan
Project Manager: AA Projects
Employers Agent: Tweeds
Contract Type: JCT 98 Design and Build
Start on Site: July 2006
Completion Date: July 2007
|
| Loreto College, Hulme (Phase 3) |
 Click for more images |
Phase 3: Design and construction of a new three storey steel frame teaching block and sports facility including demolition of existing and landscaping works.
|
Client: Loreto College
Architect: A-Cube
Employers Agent: AA Projects
Contract Type: JCT Standard
Start on Site: October 2004
Completion Date: March 2006
|
| Ashton 6th Form College |
 Click for more images |
Bardsley has successfully completed four phases of new build activity within the campus including, the design and build negotiation of a new 2 storey teaching block, design and construction of a new 3 storey performance and general teaching block and design and construction of a 1200sqm steel frame refectory.
|
Client: Ashton-u-Lyne 6th Form College
Architect: A-Cube, Halliday Meecham,
Planning & Building Associates
Employers Agents: Flynn Partnership,
AA Projects
Start on Site: Phase 1 - 1997
Completion Date: Phase 4 - August 2007
|
|